Labour Contract Agreement For Building Construction Work

10 Apr

If you do not pay according to the date indicated in the agreement, you can pay the fine. Similarly, the contractor is required to pay a penalty if he has not completed the project within the expected time frame. Even if the cost of different types of raw materials increases, the contractor should comply with the contract and it should be delivered on schedule. 19. The mobilization advance of Rs 7,00,000.00 (Only Seven Lakhs Rupees) (filling the amount of the advance indicated) is agreed by the owner, which is drawn to the contractor, empty scheck , `full cheque number and date` before the start of the work. 8. The contractor is solely responsible for respect, effort, responsibility, etc. Because of the following issues, under the relevant laws, the law and the owner is not liable for this compliance, costs, liability and damages in all circumstances. The terms and conditions agreed by both parties should be taken into account in writing. This information should be included in the agreement. 2. This contract is based on one square metre.

The cost per square metre of built area is Rs. 1750 (only seven hundred and fifty) (filling with cost). The square metre should cover all built-up areas, including balconies and utilities. Sit-outs and passages are calculated at 200 Rs per sft. You can also indicate how the site will be maintained, including monitoring workers, storing materials and where waste can be disposed of. The building will be built on the land in question in accordance with the plans, drawings, specifications and heights, as established by the architect, annexed here and marked as Annex A, with the material of the highest quality and in the most essential and similar way to that of the workers and to the satisfaction of the architect. AND THE second party is a great developer and has great experience in building large buildings and has agreed to build the house on the land in question. 20. In the event of a dispute or dispute between the owner and the contractor, the architect`s decision is binding on both parties.

7. If the contractors abandon the contract or do not start work or suspend the progress of the work for 14 days without a legal excuse under these conditions, or do not continue the work with due diligence and do not make the necessary progress that would allow the work to be completed within the agreed time frame or not to remove materials from the site or not to remove the work from the site for seven days from the time of receipt. the architect`s written notification that the materials mentioned or the works were defective and rejected or obstinately neglected by the architect in question to respect and carry out all the necessary acts, materials or things in this contract, which must be respected and executed by the owner for seven days after written notification, and the architect certifies to the owner this effect. , and in each of the cases mentioned, the owner may, despite a prior waiver, after seven days of notification by the aforementioned architect, in writing to the owners, terminate the license for the benefit of the owners and to the extent that it is the completion of the remaining works, but without undermining the powers of the architect, or the obligations and obligations of the owners , all of which remain in force, as if this agreement had not been set in this way.